RESTORATION OF KUTNO JEWISH CEMETERY - PROGRESS REPORT

Phase 0: Transfer of property grounds:04/2024
Phase 0: Creation of the Foundation:12/2024
Phase 0: First meeting of the Foundation's CouncilExpected 05/2025
Phase 0: Documentation for the wall project:Expected October 2025
Phase 3: Documentation for the ghetto project: Expected November 2026
Phase 0: Documentation for the matzevot project: Expected November 2026
Phase 1: Finding sponsors for the wall:Expected January 2026
Phase 2: Building minimal wall and cleaning:Expected October 2026
Phase 3: Restoring the matzevot:Expected March 2027
Phase 3: Transfer of matzevot to the cemetery:Expected May 2028
Phase 4: Completing the wall (optional):Expected April 2030